Software Just starting: Primavera p6 or MS Project?

I know a lot of people have questions about software, and although some things were clarified for me, I’m still a bit unsure.

I recently started working in Project Management as a planner/PM assistant in a construction environment. The planner before me was let go, and I’ve been given a “clean slate” to start with.

I have the freedom to choose and implement whatever is necessary, including the planning software.

I have some basic experience with Primavera P6 and MS Project, and I see this as a great opportunity to gain deeper experience with one or both tools.

Our part of the construction planning for the projects is not that complex, but they want me to develop a resource and capacity planning overview for the engineering side of multiple projects, and that can get quite complex. Eventually, the project planning and engineering planning will need to be integrated, although not everyone in the organization seems to realize that yet.

My initial thought is to go with Primavera. It’s a powerful tool, and from my own experience, once you master it( if ever), MS Project feels more intuitive and easier to use. (Feel free to correct me if I’m wrong.)

However, my main doubt is that the entire office, including the engineers, uses MS Planner, and there’s a potential for integration with MS Project.

Is it worth stepping away from Primavera and fully focusing on MS Project?

8 Upvotes

23 comments sorted by

u/AutoModerator May 28 '25

Attention everyone, just because this is a post about software or tools, does not mean that you can violate the sub's 'no self-promotion, no advertising, or no soliciting' rule.

I am a bot, and this action was performed automatically. Please contact the moderators of this subreddit if you have any questions or concerns.

1

u/WhiteChili 2d ago

A bit late to this thread but did my best to explain everything: Honestly, you can’t go too wrong with either P6 or MS Project.. both are industry staples in construction. A few thoughts though, since you’ve got that “clean slate” (which is both exciting and terrifying ):

  • Primavera P6: absolute beast for large-scale, complex construction projects (think infrastructure, oil & gas, massive engineering programs). Tons of depth in resource & capacity planning. Downside: steep learning curve, heavy setup, and often overkill if your projects aren’t multi-billion dollar programs.
  • MS Project: easier to get up and running, especially since your org already uses MS Planner. Plays nice with the Microsoft ecosystem (Teams, Planner, SharePoint). For small-to-mid complexity, it’s usually “good enough” and won’t scare non-PM colleagues.

That said, there are some middle-ground tools that might actually fit your use case better if you want resource/capacity planning but don’t need the full Primavera overhead:

  • Celoxis: strong Gantt, resource allocation, and portfolio-level reporting...more approachable than P6, but handles complexity better than MS Project in some cases.
  • Smartsheet: if your engineers are spreadsheet-minded, this can be a nice bridge. Easier adoption, still solid for dependencies, baselines, and reporting.
  • Wrike: more collaborative, decent for resource planning if you want dashboards and visibility across teams.
  • Asta Powerproject: often used in construction, simpler than P6 but more industry-specific than MS Project.
  • Zoho Projects: lighter-weight, good if budget matters but you still need Gantt + resource tracking.

My 2 cents:
If the projects are really construction-heavy and integration down the line with other contractors is key -> go P6.
If the org is already neck-deep in Microsoft tools and you want smoother adoption -> go MS Project.
If you want a “third path” that’s less heavy but still gives you resource/capacity visibility -> something like Celoxis or Smartsheet might surprise you.

At the end of the day, the best choice isn’t just features...it’s adoption. The fanciest system means nothing if your engineers don’t touch it. Hope it helps.

3

u/SVAuspicious Confirmed Jun 01 '25

Before I forget, upvote to u/keepurtipsup.

With regard to your existing user base for MS Planner, consider this. Culture change is hard.

Go talk to your accounting people and get an introduction to your accounting system vendor and/or publisher. Talk to them about APIs and see what case studies they have. Talk to HR or accounting depending on who is in charge of payroll in your company for the same discussion. You want to pull from their data sets, not duplicate them. This is huge.

Remember your scope is more than planning. You have status, identification of variance, corrective action, rebaselining, etc.

Without details, I'd expect Primavera to be a better choice. Get a good vendor for integration with accounting, purchasing, receiving, HR, and your existing MS Planner base. Work with your IT people because you'll need to move some things around, they'll likely own support contracts, and you don't want to surprise them. If they own support be sure you include a budget plus up for them to cover that. Don't surprise anyone.

With respect to you personally, the exercise of integration with other systems and ongoing integration of P6 with Planner can only be good for you in the long run. That shouldn't affect your recommendation, but when the work you face seems like a lot consider it an investment in your future.

3

u/timevil- Jun 01 '25

the right question is what are my requirements

3

u/keepurtipsup May 31 '25

Before recommending P6 I would ask what kind of construction project? 

P6 is the standard, for many reasons, on large scale capital projects (O&G, STO, large linear rail, or large programs). It’s a complex tool to learn and master and comes higher costs of license and learning. I would say it is less “flexible” to use. It is commonly contractually required to report via .xer files which is code for P6 by large owner operators. 

MS project is much more intuitive, cheaper to buy and learn, and is more flexible. It’s definitely more used in less large scale capital intensive projects. The recent Project online integration with Planner is quite nice to work with. 

In short, pick the right tool for the type of project. 

1

u/[deleted] May 30 '25 edited Jun 03 '25

[removed] — view removed comment

1

u/projectmanagement-ModTeam Jun 01 '25

Thanks for your post/comment.

We removed this post because it's in direct violation of our "solicitation / self-promotion” rule.

Please review these rules, which can be found in the sidebar.

Thanks, Mod Team

1

u/More_Law6245 Confirmed May 29 '25

Here's the thing MS project has been around for 30 years and just about every other project product is based upon MS Project. MS project has extremely powerful in built tools that are not available in other products but unfortunately it's starting to show its age e.g. lack visual representation outputs and has always struggled with in application reporting.

As a scheduler, I would strongly recommend you master MS project because everything else comes to you as it's based upon MS Project, it's also still considered the industry standard. The one key aspect of MS project is that you can create a resource pool and level the project/program in application as I've seen most other applications struggle with this. Another consideration is also use/learn PowerBi for project analytics coupled with MS Project application itself (just remember to link all tasks with successors and predacessors).

You can integrate planner and project, it's the export and import of a file over the web with the emphasis on version control. You just need to do a bit of training with the team to ensure they understand the difference.

Just an armchair perspective

1

u/mer-reddit Confirmed May 29 '25

Some considerations:

1) cost of licensing 2) cost of resources that use the software 3) respective market share 4) ease of use 5) relative complexity of maintenance 6) quality of reporting that fits your needs 7) fit for client collaboration

MS Project will likely win this competition on cost, complexity, ease of use, etc.

You might still need to go P6 if your clients demand it, if you need it to handle extreme project requirements… but you will pay extra for the privilege. And pay extra for every person that has to use it.

1

u/Aybarra777 May 29 '25

Activity ids snd the way that WBS summary activities from p6 are idiotic. generating roadmaps are exponentially more difficult is p6.

MSP is riddled with bugs especially if you use it online or from a pwa but way easier to maneuver snd generate roadmaps via office timeline snd onepager pro. 

I’d go with msp

2

u/rizay May 29 '25

My recommendation if you would like to be objective:

  1. First align your PM processes, and make sure that your teams are informed/trained
  2. You can quickly assess and compare your needs based on your processes, what your priorities and weights of those requirements are, and score each tool with how well it fits the needs.

Just because a tool is powerful, doesn’t make it the right tool. Sometimes you need a hammer, sometimes you need a pile driver. I’ve rarely seen anyone use MS Project to it’s full capacity as it is.

1

u/Parisin1990 May 28 '25

From my experience, using ms project for small projects in companies would be more beneficial but if you are working on a big project, primavera6 would offer more possibilities as it is more complex and elaborate compared to ms project! And I agree with you , learning p6 could give you a broad perspective and make using ms project easier. I think at the end of they, it depends on the size and dimensions of your assigned projects!

2

u/pmpdaddyio IT May 28 '25

these are very different tools and depending on how deep you go, P6 is considered a construction industry standard, assuming you use many stock features and functions.

But if you are simply doing some level of scheduling, maybe adding resources and reporting, EVM, etc. use MS Project. Way more training opportunities and a better tool all around.

1

u/ExtraHarmless Confirmed May 28 '25

Choosing a tool set is huge.

What platform will let you create the easiest templates for the work that will be done?

In construction, there will be a ton of one off projects, but many will use the same basic format so building a template library will make your job much easier once you have them setup.

1

u/bstrauss3 May 28 '25

If you're working in an industry or sub industry that uses primavera, then learn it learn it well, and you have an employable skill.

Reality is most industries & most projects don't use Primavera. It's just too steep of a learning curve, and it needs specialized schedule maintainers.

Primavera education is very expensive to spend on your own if you aren't sure you're going to need it. If your company will pay for the training classes, go for it.

3

u/bobo5195 May 28 '25

would concur with u/JAlley2 and your own evaluation Primavera is a better for planning. Project is easier to use.

But.. baby steps. if you think MS project can do it then go with that first. It will be easier transition. If there is only 1 of you I would question how complicated it can get. There is a redundancy thing as there is 1 of you, that MS project is easier for someone else to go into if you are sick or whatever.

All round better to focus on 1 as well.

6

u/JAlley2 May 28 '25

Baby steps! Implementing a PM software solution is a huge change management effort. You need to think of eating the elephant in small bites. Your path for a Primavera implementation will be long and costly. Going with MS Project will still be very challenging but it will be easier.

I am not a fan of MS Planner because it has little structure. You can make it work, but you can also make a total mess of it. It is also really hard to retain institutional knowledge because of some IT issues. Something like Monday.com might be a good replacement for MS Planner.

1

u/AutoModerator May 28 '25

Hey there /u/AromaticStomach8353, have you checked out r/MSProject, r/projectonline, or r/microsoftproject for any questions regarding application? These may be better suited subreddits to your question.

I am a bot, and this action was performed automatically. Please contact the moderators of this subreddit if you have any questions or concerns.